Georgia Power News: Vogtle Unit 3 reaches 100 percent energy output for the first time

Date: May 29, 2023

Georgia Power announced today Vogtle Unit 3 has safely reached 100 percent power, according to a press release from the company.

This milestone marks the maximum energy the unit is licensed to produce in the reactor core and is the first time the unit has reached its expected output of approximately 1,100 electric MW, which can power an estimated 500,000 homes and businesses. 

“Unit 3 is currently undergoing testing through the full range of plant operations, including safely running at various power levels and operating through real-life conditions just as it will over the next 60 to 80 years after the unit enters commercial operation,” said Kim Greene, chairman, president and CEO of Georgia Power. “As we enter the final stages of startup testing, reaching 100 percent power for the first time is an exciting milestone. It tells us we’re close to finishing the unit safely and bringing it online to power Georgia homes and businesses with reliable, emissions-free energy for decades to come.” 

Testing at the 100 percent power level is focused on the operation of the reactor, plant control systems for the reactor and support systems, and integrated plant operations, according to the press release.

Plant performance is monitored at various conditions, and data is gathered and evaluated by site engineers. With the unit reaching full power for the first time, before the unit is available for reliable dispatch other tests must be performed at this power level, according to its combined operating license. 

Once all startup testing is successfully completed and the unit is available for reliable dispatch, Vogtle Unit 3 will enter commercial operation. Unit 3 is projected to be placed in service during June 2023, according to the press release. 

Also recently, Vogtle Unit 4 began receiving nuclear fuel. Hot functional testing for Unit 4 was completed on May 1, 2022.

In April, Vogtle Unit 3 generated electricity for the first time, and successfully synchronized and connected to the electric grid. 

Company officials say the new Vogtle units are an essential part of Georgia Power’s commitment to delivering clean, safe, reliable and affordable energy to its 2.7 million customers. Once operating, the two new units will be clean energy sources that produce zero emissions. Southern Nuclear will operate the new units on behalf of the co-owners: Georgia Power, Oglethorpe Power, MEAG Power and Dalton Utilities. 

What to Read Next

The Author

Comment Policy

The Augusta Press encourages and welcomes reader comments; however, we request this be done in a respectful manner, and we retain the discretion to determine which comments violate our comment policy. We also reserve the right to hide, remove and/or not allow your comments to be posted.

The types of comments not allowed on our site include:

  • Threats of harm or violence
  • Profanity, obscenity, or vulgarity, including images of or links to such material
  • Racist comments
  • Victim shaming and/or blaming
  • Name calling and/or personal attacks;
  • Comments whose main purpose are to sell a product or promote commercial websites or services;
  • Comments that infringe on copyrights;
  • Spam comments, such as the same comment posted repeatedly on a profile.